Our proud team...  In total the project took just over five months, starting on 11th November and ending on 16th April 2014. The Estates team, 16 strong for this project, worked throughout the wettest winer on record since 1910. All bunkers have been improved and now provide you with a better choice of shot during your game of golf.

Our proud team... In total the project took just over five months, starting on 11th November and ending on 16th April 2014. The Estates team, 16 strong for this project, worked throughout the wettest winer on record since 1910. All bunkers have been improved and now provide you with a better choice of shot during your game of golf.

A little help...  For many of the bunkers diggers were used to assist with the reshaping. This included the 8th hole which was fully transformed.

A little help... For many of the bunkers diggers were used to assist with the reshaping. This included the 8th hole which was fully transformed.

The final hole, the 18th of the Cheshire golf course. Play a Summer Sizzler game to experience the new course from £40.00 per person.

The final hole, the 18th of the Cheshire golf course. Play a Summer Sizzler game to experience the new course from £40.00 per person.

All bunkers have been re-shaped and refurbished on the Cheshire golf course

All bunkers have been re-shaped and refurbished on the Cheshire golf course

Starting the project...  The Cheshire golf course bunker refurbishment project started on 11th November 2013. All golf bunkers were assessed individually and a plan was created on how to improve them taking into account the impact each had on the standard of game played. Each bunker was marked for the new shape it was going to take.

Starting the project... The Cheshire golf course bunker refurbishment project started on 11th November 2013. All golf bunkers were assessed individually and a plan was created on how to improve them taking into account the impact each had on the standard of game played. Each bunker was marked for the new shape it was going to take.

Bunker solutions...  The project included new drainage for the bunkers, in total 2000 metres of new drains were installed. Due to the previous bunker design they...

Bunker solutions... The project included new drainage for the bunkers, in total 2000 metres of new drains were installed. Due to the previous bunker design they...

Time for the turf...  With the newly shaped bunkers new turf was needed to fit with the natural shape and contours of the course. Approximately 8000 square metres...

Time for the turf... With the newly shaped bunkers new turf was needed to fit with the natural shape and contours of the course. Approximately 8000 square metres...

The previous bunkers...  On the Cheshire gof course the old bunker construction was based on revetted links which had collapsed over the years making play difficult

The previous bunkers... On the Cheshire gof course the old bunker construction was based on revetted links which had collapsed over the years making play difficult

Almost complete...  Once the bunkers had been shaped and the drains completed they were filled with sand. The project used 1000 tonnes of new sand.

Almost complete... Once the bunkers had been shaped and the drains completed they were filled with sand. The project used 1000 tonnes of new sand.

A view of the new 14th hole of the Cheshire golf course

A view of the new 14th hole of the Cheshire golf course